Politics

Trans Mountain's COVID-19 costs are now $12.5 million and growing

Last month, the Trans Mountain pipeline said it had spent about $1.2 million on keeping employees safe during the pandemic. New figures show that Trans Mountain has spent about $12.5 million on related COVID-19 expenses across the organization.

Cost 'discrepancy' leads to doubts about project's ability to stick to budget, says MP

Pipes for the Trans Mountain pipeline project are seen at a storage facility near Hope, B.C., on Sept. 1. (Jonathan Hayward/The Canadian Press)

New numbers show that Trans Mountain's COVID-19 costs are now 10 times higher than the figure the pipeline initially reported.

Last month, the federal government-owned pipeline said it had spent about $1.2 million on measures to keep employees safe during the pandemic. New figures show that Trans Mountain has actually dropped about $12.5 million on related COVID-19 expenses across the organization.

NDP MP Peter Julian said that cost "discrepancy" is generating doubts about whether the project to twin Trans Mountain's existing line between Alberta and British Columbia will come in on budget.

"I found since the beginning, since [Prime Minister] Justin Trudeau bought the pipeline, there has been a complete lack of transparency," said Julian, a frequent pipeline critic. "And so with COVID-19, I am not surprised by the discrepancy between the initial figures and new figures coming to light."

Trans Mountain president and CEO Ian Anderson first disclosed the lower COVID-19 cost during a routine annual update in November. The higher figure came to light after the Crown corporation posted its latest financial figures.

Anderson told CBC News the pipeline was not hiding the actual costs. Organizations typically report operating expenses and construction costs separately for accounting purposes, he said.

Trans Mountain spent $1.2 million on pandemic precautions within its existing pipeline operations and $11.3 million on pandemic controls for construction of the expansion, Anderson said.

WATCH: Trans Mountain president explains the pipeline's COVID-19 related costs:

Trans Mountain CEO lays out COVID-19 related costs

4 years ago
Duration 0:58
Trans Mountain president and CEO Ian Anderson says his corporation is spending about $12.5 million on COVID-19 related costs. Most of it is going to paying medical staff, testing and social distancing measures.

Anderson said he couldn't state whether these new COVID-19-related expenses would result in higher construction costs. This year, Trans Mountain reported the cost of the expansion would be increasing to $12.6 billion.

"I don't know that it will have a direct bearing on the overall cost of the project," he said. "We'll see how it affects the total costs."

Anderson said Trans Mountain has budgeted for contingencies, and its budget can absorb the additional costs.

Trans Mountain's COVID-19 measures, Anderson said, have helped the pipeline control the pandemic within the workplace. Until recently, he said, Trans Mountain had no workplace COVID-19 infections at all across the corporation. It recorded its first workplace case in November at an Alberta pump station.

"We immediately isolated all workers that had been in anywhere near contact with that worker," Anderson said. "And there has been no further infection in the workplace."

The twinning of the 1,150 kilometre-long Trans Mountain pipeline will nearly triple its capacity to an estimated 890,000 barrels a day and crude oil-carrying tanker traffic from the Westridge Marine Terminal could increase from about three vessels a month to one a day.
The twinning of the 1,150 kilometre-long Trans Mountain pipeline will nearly triple its capacity to an estimated 890,000 barrels a day. (CBC)

When it's finished, the Trans Mountain expansion project will twin the existing Alberta-to-British Columbia line and boost the pipeline's capacity from about 300,000 to 890,000 barrels per day.

According to Environment and Climate Change Canada figures, the expanded pipeline will directly produce 400,000 tonnes of greenhouse gas emissions annually, which has been factored into Canada's emission targets.

Although it's difficult to account for indirect emissions, the department also estimates the upstream emissions will add between 21 and 26 megatonnes of carbon dioxide per year, based on 2015 calculations. Those numbers don't account for land-use changes and electricity or other fuels used elsewhere.

ABOUT THE AUTHOR

David Thurton

Senior reporter, Parliamentary Correspondent

David Thurton is a senior reporter in CBC's Parliamentary Bureau. He covers daily politics in the nation’s capital and specializes in environment and energy policy. Born in Canada but raised in Trinidad and Tobago, he’s moved around more times than he can count. He’s worked for CBC in several provinces and territories, including Alberta and the Northwest Territories. He can be reached at david.thurton@cbc.ca

Add some “good” to your morning and evening.

Your weekly guide to what you need to know about federal politics and the minority Liberal government. Get the latest news and sharp analysis delivered to your inbox every Sunday morning.

...

The next issue of Minority Report will soon be in your inbox.

Discover all CBC newsletters in the Subscription Centre.opens new window

This site is protected by reCAPTCHA and the Google Privacy Policy and Google Terms of Service apply.