Less than one in five federally funded car charging stations are operational

More than 43,000 electric vehicle chargers have been funded over the last seven years under the federal government's two main EV infrastructure programs. But data supplied by the Department of Natural Resources shows fewer than one in five are actually operational.

Government invested $768M between 2016 and 2027 to buy and install nearly 90,000 chargers

Two hands can be seen putting an electric charger into the side of a white car.
An analysis drafted for the federal government says Canada likely will need 52,000 chargers in place by the end of 2025, and about 200,000 by 2030, to meet national sales targets for EVs. (Hannah Yoon/Canadian Press)

Two different federal infrastructure programs have provided funding for more than 43,000 electric vehicle chargers since 2016, but new data shows fewer than one in five of them are actually operational.

The information provided by Natural Resources Canada came as Energy Minister Jonathan Wilkinson visited Quebec City Wednesday to announce another $25 million to fund 1,500 EV chargers in Quebec.

That announcement is the latest in a series of EV charging announcements in local communities across Canada. The government aims to help build 84,500 chargers by 2029.

Natural Resources Canada launched an initial program to fund up to half the cost of installing public fast EV chargers, natural gas stations and hydrogen refuelling centres in 2016. Three years later, it introduced a second program expanding the scope to include other types of chargers.

Data supplied by the department upon request says 43,046 chargers have been funded through both programs, but only 7,644 are working.

The first program, which ended in 2020, provided funding for 1,096 EV chargers and almost 20 per cent are still not operational. It also funded 22 natural gas stations and 15 hydrogen stations — about 40 per cent of each have yet to start working.

The second program, which started in 2019 with a $280-million five-year investment, was meant to install 33,500 electric vehicle chargers by 2025. It was later expanded to run until 2027 with another $400 million in funding.

Natural Resources Canada says as of Aug. 21, 42,007 chargers have been "selected for funding" and 6,697 of those are operational.

The department's database lists 23,000 operational public charging ports in about 9.800 locations across the country, including those funded through federal programs and those paid for privately.

The public funds only pay for up to half the cost of the equipment and installation.

Wednesday's announcement includes funds for Hydro-Quebec, Les Petroles, Bell Canada and the Montreal-Trudeau International Airport.

An analysis for the federal government by the research firm Dunsky Energy and Climate says Canada likely will need 52,000 chargers in place by the end of 2025 and about 200,000 by 2030 to meet national sales targets for getting more electric vehicles on the road.

A report on Aug. 25 by Electric Autonomy Canada said electric vehicle sales surged to nearly 11 per cent of total market share nationally in the spring, the highest proportion ever.