Ottawa·Analysis

How the bar for LRT trial running was lowered — then lowered some more

Wednesday marks the second last day of testimony at the inquiry into Ottawa's Confederation Line. Yesterday, the inquiry heard the city used 'discretion' to overturn what likely would have been a 'fail' day during the LRT's 12-day testing run.

Inquiry heard Tuesday that trial run team used 'discretion' to give line a pass

O Train
The three-and-a-half week trial period for the Confederation Line has taken up a lot of oxygen at the Ottawa LRT public inquiry in the past two weeks. (City of Ottawa)

Among the overwhelming swells of information pouring out of the Ottawa light rail public inquiry each day, there are always a few moments that rise above procurement financial details, engineers' technical talk, and political rhetoric

On Tuesday, there was the revelation that former city transportation general manager John Manconi now works as a consultant at STV Inc., the firm that advised the city throughout the Confederation Line project and which the city tried to characterize as an independent third party to oversee the LRT's post-derailment return to service

Later in the day, we heard the LRT operator of the train that derailed leaving Tremblay station last September was communicating with the control room about the smell of human feces on the train.

That led Michel Valo, the lawyer for train-maker Alstom, to suggest the operator was distracted and didn't notice clouds of dust and ballast flying onto the platform or the train scraping on the platform edge.

A lawyer for Alstom suggested during the inquiry that the operator of the train that derailed last September was distracted by the smell of human feces on board. (Nicholas Cleroux/Radio-Canada)

And then just when you think there's nothing more you can — or want to — learn about the 12-day trial run period, you find out you're wrong.

Because on Tuesday we also discovered that on top of agreeing to (and possibly even suggesting) the idea of lowering the criteria for what was supposed to be 12 consecutive days of a near-perfect simulation of full service, the city also used its "discretion" to issue a pass on a day that should likely have been a fail.

The city lowered the bar for trial running, then lowered it again. 

No straight answers running until now

Since late August 2019, it's been difficult to get straight answers about how and when the trial running — that last, critical test phase of the LRT — was changed.

Until now.

From the intense, frequent questioning on the subject, it's clear the commission running the inquiry is every bit as interested in the details of the trial as we are, and possibly for reasons more than just the scoring.

Through testimony from a number of witnesses and information from hundreds of documents posted to the inquiry's website, we've learned the city changed its contract with consortium Rideau Transit Group (RTG) to accept 13 trains instead of 15, beginning on Aug. 16, 2019.

The next day, on Aug. 17, the city and RTG reverted to previously agreed upon criteria from 2017 that would lower the LRT's reliability threshold. Instead of covering 98 per cent of the regularly scheduled kilometres for 12 straight full-service days, Confederation Line trains would only have to hit 96 per cent for nine of them.

The inquiry has heard from several witnesses that 98-per-cent reliability was an unrealistic target for a new system and that 96 per cent would still provide a good customer experience. 

It was certainly unrealistic for the Confederation Line, at least in the summer of 2019. Over the 24 days of the trial run period, from July 29 to Aug. 22, the LRT scored 98 per cent only five times. (Notably, the same witnesses who've referred to the 96 per cent target as more than adequate have never mentioned the part about how the system performed terribly for one-quarter of the testing period, but still passed.)

And there's one more detail about the 2017 criteria that matters: there could be no three consecutive days below 94 per cent.

Scoring team used 'discretion' to pass 1 day

That's because the scorecards show there were actually four straight days where the Confederation Line did not achieve 94 per cent reliability. They were:

  • Aug. 13, 2019: 91.7 per cent
  • Aug. 14, 2019: 93.9 per cent
  • Aug. 15, 2019: 92.3 per cent
  • Aug. 16, 2019: 92.3 per cent

We've heard from witnesses that reliability around 90 per cent provides, in former RTG CEO Peter Lauch's words, a "horrendous" customer experience. So these are not results to write home about.

The middle two days — the 14th and 15th — were deemed "repeat" days by the trial run evaluation team, and for some reason were not counted in the consecutive day tally.

Former RTG CEO Peter Lauch has testified that it was former OC Transpo boss John Manconi's idea to lower the trial test criteria. (Jean Delisle/CBC)

And then we come to Aug. 16. After hearing how the day was doing on a WhatsApp group chat among city transit officials and their consultants, Manconi wrote at 5:13 p.m: "We can't loose [sic] the day."

Later in the evening, the group was told there was a train stopped due to an on-board computer problem, Manconi repeated his plea: "Launch a spare? Don't loose [sic] the day."

They didn't lose the day — which would have extended the trial running into September. Instead, they used their discretion to issue a pass.

Decision not made in 'isolation'

Troy Charter, who was OC Transpo's representative on the trial running review team, testified Tuesday that the issue wasn't due to train issues but poor decisions by the maintenance team.

One worker decided to move a stopped train at Tunney's Pasture to the maintenance storage facility, Charter said. But it then proceeded to fail out on the main line, slowing down service in the late afternoon and evening hours. 

The other issue, said Charter, was that Alstom wasn't acting as if there were customers on those trains and was spending too much time trying to solve issues while the trains were on the track, instead of getting them off the line.

The next morning, when discussing the scoring — a pass-or-fail decision was typically made by the review team the day after — Charter shared the Aug. 16 score with the chat group and told them what happened.

"So we pass the day?" asked Manconi.

Charter answered that he would note the maintenance mistakes on the scorecard and "recommend we use discretion and pass the day."

When the city's lawyer asked Charter to explain the process, he said it wasn't a decision he'd make "in isolation."

"The decision of the trial run review team needs to be part of [it]," Charter said. "And we had the independent certifier as part of it."

OC Transpo director of transit operations Troy Charter, seen here in 2019, recommended the trial run evaluation team use 'discretion' to pass the Confederation Line on a day that likely would have been a fail. (Matthew Kupfer/CBC)

This might sound reasonable, except for a few issues.

First, Aug. 16 was the fourth consecutive day that the reliability of the Confederation Line scored below 94 per cent, which should have triggered a restart. 

Second, the fact that the score review process was overseen by an independent certifier is virtually meaningless. The certifier, as CBC reported earlier this week, is there to check off the boxes of the contract requirements, not get into the weeds of the scoring.  

In an earlier discussion on the use of the city's discretion, city rail director Michael Morgan told the WhatsApp chat group that "if we want to give them a pass, the [independent certifier] may give an opinion but is unlikely to intervene."

In fact, the independent certifier team leader, Monica Sechiari of Altus Group, wasn't even at the trial testing, leaving the oversight to a junior colleague who'd only been out of college for four years.

And finally, using discretion to wave away a maintenance mistake that would have caused an actual disruption seems to counter the very purpose of the trial running, which is to mimic full rail service with real people. 

More than just percentages

The trial run experience was about more than just percentage targets. It reflected so many of the issues being investigated as possible factors that led to early problems with the Confederation Line. 

Did the use of milestone payments in the contract put financial pressure on the builders to finish faster than they should have? Was there undue political pressure to open the system? (Mayor Jim Watson had invited a slew of VIPs to a handover ceremony on Aug. 23, 2019, two days before the trial running was completed.) 

Was the maintenance team ill-equipped? Did it shoulder an unfair burden, trying to stay on top of a system that was approved again and again, despite its documented defects? How were the corporate and public service leaders behaving in this complex and stressful partnership?

These questions are apparent in the trial running, which perhaps is why the commission has come back to those three-and-a-half weeks in the summer of 2019 again and again.

Alstom's Richard France and the city's former chief safety officer Brandon Richards are set to testify Wednesday, the penultimate day of the public hearings.

ABOUT THE AUTHOR

Joanne Chianello

City affairs analyst

Joanne Chianello was CBC Ottawa's city affairs analyst.