Taltson power plant back online after wildfire shutdown
N.W.T's Taltson hydroelectric power plant is back online but Fort Resolution, Fort Smith and Hay River remain on diesel-generated power until transmission lines can be re-energized.
N.W.T's Taltson hydroelectric power plant is back online but Fort Resolution, Fort Smith and Hay River remain on diesel-generated power until the transmission lines can be re-energized.
The Northwest Territories Power Corporation shut down the Taltson plant around 6:30 p.m. Sunday because a forest fire was approaching power transmission lines.
The power corporation says it's not clear when the communities will be back on hydro power.
The corporation needs the OK from the Department of Environment and Natural Resources to check the power lines before they can be re-energized.