Man's foot partially amputated in workplace incident, OHS lays charges

RJG Construction is facing nine violations of the Occupational Health and Safety Act related to the 2017 incident.

RJG Construction facing 9 violations related to 2017 incident

An employee had to have part of his foot amputated after a workplace incident on a pier at St. John's Harbour. (Submitted by Alick Tsui )

A St. John's construction company is facing nine charges under the Occupational Health and Safety Act after a worker's foot had to be partially amputated after a workplace incident. 

The man, who was 34 years old at the time, was working for RJG Construction on a wharf at the St. John's Harbour in October 2017. He fell into the water — while wearing a life-jacket — and co-workers rescued him by boat. 

A stop-work order was ordered but lifted less than a week later. 

The violations under the act relate to the company's alleged failure to:

  • Provide and maintain a safe workplace.
  • Provide necessary information, instruction, training and supervision.
  • Ensure workers and particularly supervisors are made familiar with the hazards.
  • Ensure safe work procedures are followed.
  • Ensure safe work procedures promote the safe interaction of workers and their work environment.
  • Ensure the use of a mobile crane meets applicable requirements.
  • Implement its OHS program.
  • Ensure the OHS program includes written safe work procedures.
  • Ensure material is placed in a secure manner that does not constitute a hazard to a worker.

The charges were laid after an investigation by the OHS Division of Service NL.

A court appearance is scheduled for July 16 in St. John's. 

Company previously cited by judge for incompetence

RJG Construction was ordered by a Supreme Court judge in February 2018 to pay Marine Atlantic $1.3 million for its failure to complete wharf work in Argentia.

While both parties had accused the other of breach of contract, Justice James Adams ruled against the construction company.

"The real cause of the delays was incompetence on the part of the management of RJG in failing to properly plan for the needs of the project with skilled staff, equipment and work scheduling," Adams wrote in his decision, released Feb. 26, 2018.

Specifically, Adams said, the company did not have adequate skilled tradespeople to complete the work, or appropriate cranes or barges.

Read more from CBC Newfoundland and Labrador