Hearings begin on fate of wetlands impacted by Calgary ring road
At issue are 4 wetlands that will be filled in to make way for the span
Hearings got underway on Monday to determine whether four wetlands can be filled in to make way for the southwest Calgary ring road.
A total of 24 wetlands, including the four in question, were slated to be filled in along the Elbow River as part of the construction. Permits remain in place for the remaining 20.
- Southwest Calgary ring road construction continues despite environmental appeals
- Construction of southwest ring road will destroy popular beaver pond, protesters say
"Alberta has to stop bulldozing and wiping out our wetlands, especially since we've already experienced 2013 flood and 2005 flooding," said Allie Tulick, one of two people who filed successful appeals against the work.
"We can design roads to move around wetlands, go over water areas. We have bridges. We do it all the time."
Berm-style bridge
Currently, a berm-style bridge is planned to bring the ring road over the Elbow River and as part of the project the construction company was granted a permit to permanently fill in 24 wetlands.
The design of the bridge is not in question during the hearings, despite the efforts of Tulick and her group, YYC Cares, to force a redesign.
Construction on the $1.42-billion project continues during the appeal process.
3 possible outcomes
EAB spokesman Gilbert Van Nes says there are three possible outcomes from the hearings.
"That the approval here be confirmed, which means everything's fine; reversed, which means we have to go back to the drawing board; or varied, which means the board will make changes to the approval that would allow the project to proceed," he said.
The board expects to issue a decision within 20 days.
- MORE CALGARY NEWS | Volunteers save 25,000 fish from canal deaths this year
- MORE CALGARY NEWS | Police search for $10K wheelchair stolen from 93-year-old Calgarian
Corrections
- A previous version of this story said the hearings would determine the design of a bridge over the Elbow River. The hearings only impact the filling-in of four wetlands as part of construction.Oct 23, 2017 8:01 PM MT
With files from Colleen Underwood