PEI

Work on Province House restoration will stretch beyond the end of 2023

The second of four phases for the Province House restoration project is now complete, but it’s still unclear when the Charlottetown landmark will reopen to the public, when it will resume hosting the P.E.I. Legislative Assembly, and what the final cost will be.

Final cost to rehab Charlottetown landmark still unknown; tenders still being issued

Nicole Gallant
Nicolle Gallant, project manager for Parks Canada, says the cost is justified to commemorate the historical significance of Province House. (Wayne Thibodeau/CBC)

The second of four phases for the Province House restoration project is now complete, but it's still unclear when the Charlottetown landmark will reopen to the public, when it will resume hosting the P.E.I. Legislative Assembly, and what the final cost will be.

The project began in 2015, the year Wade MacLauchlan was sworn in as premier and led the Liberals to a third consecutive term in government, and P.E.I. set a record for snowfall with 550 centimetres having fallen by April. 

A May 2014 commitment of $10.2 million was meant to cover "initial areas of highest concern to address critical structural issues in the building." That work was originally set to be completed three years later.

But the project faced numerous setbacks, including rot found inside the walls, restrictions imposed as the COVID-19 pandemic set in, and a mid-project change in sub-contractors.

Parks Canada, which is overseeing the project, eventually said it was aiming to have all the work completed at the end of this year — five years behind schedule — at a cost of $91.8 million.

But those numbers are now being revised, said Nicolle Gallant, the project manager for Parks Canada.

"It's very complicated," she said. "We just really didn't know what we were getting into until we were in here and we were really opening up the walls and saw the state of the masonry and saw the water was coming in from the roof. We really couldn't have known."

Exterior of Province House
Phase 3 focuses on preserving the character-defining elements of Province House. (Aaron Adetuyi/CBC)

Phase 2 of the project, which began in 2018 and finished in 2022, involved much of the masonry work, the roof and the conservation of 101 windows.

Phase 3 underway

Phase 3, which is now underway, focuses on preserving the character-defining elements of Province House, according to Parks Canada. It includes painting, as well as taking care of the heritage woodwork and flooring. There are also upgrades for operational components such as fire and safety systems, information technology and audio-visual, plumbing, electrical and ventilation systems. 

The fourth and final phase involves the development of the new inclusive, multi-perspective visitor experience and interpretive exhibits. 

Parks Canada said it can't determine the final cost until all the tenders come in, noting that some of the bids contractors submitted were higher than anticipated. It also said funding was approved in stages after the May 2014 allocation of $10.2 million, as the need for further restoration projects became apparent. 

A peek down the elevator shaft at Province House.
A peek down the elevator shaft at Province House. (Wayne Thibodeau/CBC)

The end date is also yet to be determined, though one thing is certain: The work won't be finished by the end of 2023.

Tim Chandler, senior project manager with Public Services and Procurement Canada who has been involved with the Province House renos since the beginning, said the market has changed in the last eight years.

"Trades are in shorter supply, materials are taking longer to procure. All those things are impacting cost and schedule."

Province House
Work currently underway includes upgrades for operational components such as fire and safety systems, information technology, audio-visual elements, plumbing, and electrical and ventilation systems. (Wayne Thibodeau/CBC)

The Canadian Taxpayers Federation has been critical of the cost overruns, but Gallant believes it's still money well spent, given the historical significance of the building.

P.E.I.'s legislature began meeting at Province House in 1847, nearly two decades before it hosted the Charlottetown conference that led to Canada's Confederation. The building is the second-oldest seat of government in Canada, after the Nova Scotia House of Assembly in Halifax.

"We have so much historical significance in this building and I just think it's really important to try and commemorate that as much as we can," Gallant said.

Corrections

  • An earlier version of this story said Wade MacLauchlan won a third term as premier in 2015. In fact, he was sworn in as premier and led the Liberals to a third consecutive term in government.
    May 04, 2023 10:44 AM EDT

With files from Wayne Thibodeau