SNC-Lavalin warned Quebec that superhospital may cost millions more
Engineering giant advised officials it carried out work not included in contract
![](https://i.cbc.ca/1.1656545.1401399219!/httpImage/image.jpg_gen/derivatives/16x9_1180/hi-muhcsuperhospital-852-8col.jpg?im=Resize%3D780)
The McGill University Health Centre superhospital may end up costing more than its current $1.3 billion dollar price tag.
Sources have told Radio-Canada's investigative program Enquête that engineering firm SNC-Lavalin may claim an additional $191.5 million for the project.
Sources also told Enquête that the bulk of that sum — $171 million — is for work that is not considered to be part of the initial contract with the MUHC — such as building a bridge linking the hospital to its parking lot.
The engineering giant may also claim an additional $21.5 million for work stoppages at the site.
Internal note
Radio-Canada obtained an internal note that was sent to the provincial government in December.
It indicated that SNC-Lavalin thought the project was delayed with work stoppages because of slow decision-making by the MUHC.
The note also said that the health ministry should expect a bigger bill.
The sources who spoke to Radio-Canada said the matter is still under discussion.
No one from the MUHC or SNC-Lavalin would comment.