This crane is helping REM workers build the new light rail more quickly and quietly

Method is considered more effective, less messy than pouring concrete

Image | horizontal crane

Caption: A long beam carries prefabricated concrete segments, each weighing about 50 tonnes. (Charles Contant/CBC)

Delivery of the new, $6.3 billion light rail transit system is rapidly approaching and crews are using a new construction method they say is more effective — and less messy — than pouring concrete.
The horizontal crane is called a launching gantry.
Two cranes will build an elevated platform of about 13.5 kilometres all the way to Sainte-Anne-de-Bellevue.

Image | concrete segments REM

Caption: It's the first time the system's being used in Quebec. (Charles Contant/CBC)

REM workers said the system is better for people living near the sites.
"This is a way to reduce the impact on the environment, on the people around," said Stefan Balan, the director of the Sainte-Anne-de-Bellevue—Airport line.

Image | REM horizontal crane

Caption: Two cranes will build an elevated platform of about 13.5 kilometres all the way to Sainte-Anne-de-Bellevue. (Charles Contant/CBC)

The long beam carries prefabricated concrete segments, each weighing about 50 tonnes.
Workers lock the pieces into place to build the track bed, and the machine slides back to tackle the next span.
Watch: The horizontal crane being used to build the elevated REM platforms.

Media Video | CBC News Montreal : New REM construction method

Caption: Launching gantry used to build elevated REM platform.

Open Full Embed in New Tab (external link)Loading external pages may require significantly more data usage.
It's the first time the system's being used in Quebec. The machine can finish one 40-metre span in about two days,
The slabs are made in a factory near Drummondville.

Image | REM construction

Caption: Workers lock the concrete pieces into place to build the track bed, and the machine slides back to tackle the next span. (Charles Contant/CBC)