Nova Scotia Power seeks $110M for repairs at Wreck Cove hydro plant
Tom Ayers | CBC News | Posted: March 3, 2020 10:00 AM | Last Updated: March 3, 2020
Power company says rebuilding is cheaper than shutting down and decommissioning at nearly $500M
Nova Scotia Power is requesting regulatory approval for a $110-million refurbishment of the Wreck Cove hydroelectric station in Cape Breton.
In documents filed last week with the Utility and Review Board (UARB), Nova Scotia Power said its largest hydroelectricity operation was built more than 40 years ago and needs major work to last another 40 years.
The company declined comment while the issue is before the UARB.
In its filing, the utility said wind power is variable and coal is being phased out because of pollution.
It said the Wreck Cove hydro plant is critical to ensuring a steady power backup and in meeting greenhouse gas emissions targets.
Generators, turbine parts need replacement
The company said the station's two generators need to be replaced and the majority of the turbine parts need to be refurbished.
That work will make up about 80 per cent of the project.
The remaining work — replacing breakers, switches and cooling gear, among other things — is expected to be done later in a second phase.
The power company said shutting the plant down and decommissioning it would amount to almost $500 million, making its $110-million repair plan the least costly option for consumers.
There is no indication yet how the project will affect power rates and no date has been set for a hearing.
Some of the details are redacted or have been submitted and held in confidence by the UARB.
Nova Scotia Power said in its application that was necessary to protect suppliers and to ensure competition when it comes time to hire contractors to do the work.