1,100 Edmonton intersections need upgrades to support smart signals

Cost to upgrade all intersections estimated at $150 million

Image | traffic calming

Caption: A new city report estimates it would cost approximately $150 million to upgrade the traffic signals in Edmonton for smart technology. (CBC)

Some 1,100 traffic intersections in Edmonton need upgrades to support smart technology, a new city report shows.
The report estimates it would cost approximately $150 million to get the city's traffic signals up to speed.
The upgrades would add adaptive signals to the intersections. Adaptive signals use sensors to gauge traffic flow and volume and can adjust the timing of the lights. The smart signals have been shown to improve travel and wait times.
The report in front of the city's urban planning committee Tuesday recommends doing a pilot project to test certain intersections.
Coun. Andrew Knack thinks the city should move faster and start budgeting for signal upgrades this fall.
"It's not like we're trying to figure out whether this technology is here to stay, rather it is here to stay, so part of my thinking is that is there really a point in piloting it anymore then?"
Several North American cities, including Pittsburgh and Toronto, are testing adaptive signals. Administration will monitor the results of pilot projects in other cities.
Companies that supply adaptive signalling claim the smart lights can reduce travel time and delays by nearly 40 per cent compared to conventional traffic signals.
The city has flagged two kinds of intersections requiring attention: Ones that are compatible with adaptive signalling but still need upgrades to their detection, cabling and auxiliary devices and ones that aren't compatible and will cost more to upgrade.
There are 700 intersections that need upgrades at a cost of $100,000 each and 400 signals that require replacements at a cost of $200,000 each.
Knack thinks it's worth investing in the adaptive signals to tackle congestion problems.
"If you're investing in technology that actually reduces wait times and travel times, in fact we could even be improving upon congestion."
Knack plans to ask city staff if it's feasible to skip the pilot and set money aside for the upgrades in the next budget cycle.